Pekat Expands Kulai Johor Solar Project to 135MWac in RM186.5 Million Deal
Pekat Expands Kulai Johor Solar Project to 135MWac in RM186.5 Million Deal
Pekat Group has significantly expanded a large-scale solar project in Kulai, Johor, more than doubling its capacity and increasing the overall project value to approximately RM186.54 million.
Expanded from an initial 63MWac following additional engineering and construction works.
Initial capacity before the project expansion.
Revised solar generation capacity.
Value of additional EPCC works.
Enlarged contract value after the variation.
Pekat More Than Doubles Kulai Solar Capacity
Pekat Group announced that its large-scale solar project in Kulai, Johor has been expanded from 63MWac to 135MWac.
The expansion follows additional engineering, procurement, construction and commissioning works under a contract variation.
The additional works more than double the project's planned alternating-current generation capacity.
Total Project Value Rises to RM186.54 Million
The additional EPCC works are valued at approximately RM100.86 million.
This increases the overall contract value from approximately RM85.7 million to RM186.54 million.
Original project contract value.
Additional EPCC scope from the expansion.
Total revised project value.
The Expansion Represents Phase Two
According to The Star, Kenanga Research identified the contract variation as phase two of the existing Kulai solar development.
More Phases Could Follow
Kenanga Research said its channel checks suggest the wider project could ultimately involve around 500MW of total capacity, indicating that further phases may potentially be awarded. This 500MW figure is an analyst estimate rather than a confirmed capacity announced by Pekat.
What EPCC Work Involves
Large-scale solar developments require multiple engineering and construction disciplines before commercial generation can begin.
Engineering
Technical design and system planning for the expanded solar generation facility.
Procurement
Procurement of solar-related equipment and electrical infrastructure required for the project.
Construction
Physical development and installation of the enlarged solar power infrastructure.
Commissioning
Testing and final commissioning before the facility enters commercial operation.
The Johor Solar Expansion Could Support Pekat's Earnings Growth
Kenanga Research described the contract variation as a positive development for Pekat and said it supports earnings growth through the financial year ending December 31, 2026.
Approximate value used by Kenanga Research for the additional works.
Based on an assumed pre-tax margin of 8%.
The research house maintained its outperform call.
Why This Matters for Johor
The Kulai expansion adds to Johor's growing renewable-energy investment ecosystem, alongside rising demand from manufacturing, industrial facilities and digital infrastructure.
Large-scale solar developments can also support the wider transition toward lower-carbon electricity and strengthen Johor's attractiveness for companies with sustainability and renewable-energy requirements.
Renewable Energy Growth
Utility-scale solar capacity can support Malaysia's broader renewable-energy transition.
Industrial Demand
Manufacturing and technology companies increasingly consider renewable energy access in site selection.
Electrical Infrastructure
Solar projects require grid connections, substations and supporting electrical infrastructure.
Kulai Investment Corridor
Renewable-energy development adds another layer to Kulai's expanding industrial and infrastructure ecosystem.
Looking for Industrial Land or Large Development Sites in Johor?
We assist investors and companies looking for industrial land, factories, warehouses and Built-to-Suit opportunities across Johor, including locations suitable for large-scale and infrastructure-intensive development.
Pekat Group: “Pekat Expands Johor Large-Scale Solar Project to 135MWac”
The Star: “Johor solar deal positions Pekat for growth”, published 5 June 2026.
Read Pekat's official announcement →
Read The Star report →
29 Aug 2026